Monday, January 22, 2018

Plans for Garrison Park Improvements Taking Shape

Progress on the preliminary plans for the improvements to Crossville's Garrison Park has been made and Tammy French, Crossville Parks and Recreation Department Director said that parts of the project will start going out to bid in about 45 days. 

In addition to a large playground and splash pad, the existing basketball court will be resurfaced, sidewalks constructed and a multi-purpose building will be built.  The building will house the pumps for the splash pad, 4 family restrooms and at the front will be a covered picnic pavilion.

Close up of plans for Phase 1 of Garrison Park

In the plan above you can see that there will be a large green space between the playground on the left and the splash pad on the right for play and frisbees and catch.  

French said that the splash pad would be 53 feet wide and 78 feet long with a variety of water structures.  A toddler area will be in one end and items for larger kids and even adults would be part of the installation.  The splash pad feature will use recirculating water that is filtered and treated.  

The playground is designed to be all-inclusive and will measure 60 feet wide and 100 feet long.  It will include swings and a play structure with a variety of activities.  

Plan showing the full park

In addition to oversight by Lose and Associates Engineers and the Tennessee Department of Environment and Conservation, the project will be managed by a general contractor.  The playground and splash pad are expected to be bid separately to firms that specialize in those installations.  Work is expected to continue on the project much of this year. 

Thursday, November 30, 2017

Garrison Field Bleachers Coming Down in Preparation for Park Redevelopment

Bleachers used for Baseball and early County Fair Events
to be replaced by new park attractions.

Crossville city crews have been working this week to begin the process of recreating Garrison Park using state grant funds to improve the centrally located park.

The removal of the 60 year old bleachers has been controversial as some wanted to see the structure saved but because work to improve the bleachers would require upgrades to ADA standards, the city council decided to remove them.

Plans for the park include a picnic area, playground, walking trail, basketball courts and a public restroom facility.  The cost of the park redevelopment totals approximately $1 million with the state grant covering half the cost or $500,000. 

Previous story on Garrison Park history and condition from August 2016

Final design plans for the park are currently being prepared and bids on the project are expected to go out in early Spring 2018. Plans are that the baseball field A will be retained at the park. Original plans called for a multi-purpose field as phase 2 of the park redevelopment. 

Garrison Park gate File Photo


Saturday, June 17, 2017

After assurances fence and Field "A" are safe, council moves forward on Garrison Park improvements.

Crossville city council agreed to move forward with the planned redevelopment of Garrison Park while the city plans to keep the perimeter fence around the park and the so called Field “A” intact.

The city received a $500,000 grant toward the project to remove the late 1940's grandstand, put in a playground, a splash pad, a new basketball court and a rest room. The city is to match the state funds for the total cost of $1 million for phase one of the project. It is unclear if or when additional work might be done on the park.
Initial design plan for Garrison Park improvements

The action on the June agenda was a budget amendment for the current fiscal year to move forward with contracts for design and grant administration. Council members Danny Wyatt and Pamala Harris both expressed concern about the need to retain the fence around the park and the larger ball field at the park.
L-R: City manager Geg Wood, council members J.H. Graham
and Danny Wyatt, Mayor James Mayberry and council members
Pamala Harris and Scot Shanks. 

The item was pulled out of the consent agenda for separate action and discussion by councilman J. H. Graham and councilman Danny Wyatt addressed his concerns saying, “I'm all about building this park over there but I want it done correctly.” Wyatt mentioned the fence around the park and said it would be very expensive to replace.

Entrance to Garrison Park

The other item Wyatt sought clarification on is the ability to leave Field A since it is part of the second phase of the project that is not currently funded or under consideration. Wyatt also questioned why if the grandstand was part of Field A was it part of this project.

Mayor James Mayberry responded, “The bleachers were one of the biggest health and safety issues with the whole deal and why it was a priority.”

Councilwoman Pamala Harris said her biggest concern was if there was a guarantee that the city could conserve Field A and conserve the fence. “I'm just uncomfortable unless I know these things can be saved,” added Harris.

Check the great lineup of vehicles at

Mayor Mayberry said that he had a verbal assurance that the state would use common sense about the safety provided by the perfectly good fence and there should be no reason to remove it. Mayberry added that he had been to the Tennessee Municipal League meeting and found out that park designers like to have parks feel more open without fences but that safety is a concern.

Mayberry said that with the removal of the grandstand a backstop fence would be required as well.

Discussion of a possible big tournament in the Fall came up and it was estimated that no work on the field would start before the first of 2018 and the grant funds must be used within 2 years.

Video of council discussion on Garrison Park

With one final reading still to go, the city will request an answer in writing by a special called meeting on June 29th when the final reading is expected to take place along with the final reading of the 2017-18 budget.

With that, Mr. Wyatt made the motion to approve contingent on getting an answer by the third reading and was supported by Mr. Graham and the motion passed unanimously.

The longtime park has been the location of a baseball field since the 1920's according to property records and at one time was the location where the Cumberland County Fair was held.


Monday, May 22, 2017

Council approves moving forward with Garrison Park plans and Centennial Park splash pad.

“I don't know why we wait til the very end on projects and decide to not do them,” commented Crossville Mayor James Mayberry during a discussion of the next steps on the redevelopment of Garrison Park.

“We've already executed the contract,” pointed out Mayberry after councilman Danny Wyatt sought to delay the project with a motion for the city attorney to review the contract and report back to the council at their next meeting. Councilman J. H. Graham seconded Wyatt's motiuon for the purposes of discussion.
Council discussing Garrison Park. L-R J.H. Graham,
Danny Wyatt, Mayor James Mayberry and Scot Shanks

City manager Greg Wood advised the council that the things in the grant would have to be done but there was some flexibility on matters of sidewalks and fencing.

Mayberry stated, “I've got it on pretty good authority they will use common sense in our disucssion request on the fence” and the city has sent a letter in reference to that.

Wyatt said his questions came up “because we wasn't told all this on the front end.” Mayberry said that the city could keep Field A at Garrison Park because the planned “multi-use field” is part of phase 2 of the plan and currently the funding and plans were only for Phase 1.

The motion failed in a tie vote with Wyatt and Graham voting in favor and Mayberry and councilman Scot Shanks opposed.
Council discussion on Garrison Park and
Centennial splash pad.

Mayor Mayberry moved that the city approve the contracts with Community Development Partners, the grant administrator and Lose and Associates, the engineer firm to design the work. Mayberry's motion also included first reading of a necessary budget amendment. Mr. Shanks gave a second for the motion.

With no further discussion, the vote included yes votes from Mayberry and Shanks. Wyatt voted no and Graham abstained. With councilwoman Pamala Harris not yet at the meeting and the abstention counted with the yes votes, the motion was approved.

Council moved then moved to discussion of the addition of a splash pad at Centennial Park to match the one planned for Garrison. Mr. Wyatt moved that the city put out a request for proposals for the design and construction of a splash pad.


Discussion revealed that the council had previously requested Hart Freeland Roberts to prepare a design for such an installation but no contact was ever brought back to the the city. Manager Wood has recommended that the previous action be rescinded and a new request be circulated. Mr Wyatt amended his motion to rescind the previous action.

Manager Wood suggested the city might be able to have to the two splash pads done together and be able to save some money on the work.


Wyatt's motion passed unanimously with yes votes from all four council memebers present. Ms. Harris arrived at the meeting following these actions.  

Tuesday, May 16, 2017

Special Called council meeting Thursday 5 PM on Garrison Park, splash pad and sidewalks. Budget work follows

Crossville city council meets in a called meeting followed by a work session on Thursday starting at 5 PM in Crossville city hall.

The called meeting will include discussions and possible action on at least two items deferred from the regular council meeting last week. One topic is moving forward with the plans to redevelop Garrison Park on Fourth Street and the other is another round of discussion on downtown sidewalks, a topic that has been around since plans were first put forth for downtown improvements 14 years ago.
Garrison Park entrance

The council put off action to move forward and approve contracts for grant administration and engineering for the Garrison Park project until they got a response from the Local Parks and Recreation Fund (LPRF) about keeping the fence around the park and keeping the larger baseball filed known as Field A. Plans remain to remove the old grandstand structure built around 1949 as it is in poor condition and not ADA accessible.

The redevelopment plan for the park includes a splash pad, playground, new restrooms, a walking trail, and redoing the basketball court. The city was awarded a 50/50 match grant of $500,000 for the project.
Example of Splash pad in Cookeville's Dogwood Park

A discussion is also planned on a splash pad proposed for Centennial Park. The project was discussed last year and a motion to have the then interim city manager negotiate a contract with engineers on such a project. No contract was ever brought back before council and current city manager Greg Wood is recommending the council seek a design/build contract on such a project.

Council will hear information about the city manager and engineers recent meeting with TDOT officials on the sidewalk and Main Street paving project. TDOT will correct some of the downtown sidewalk corners to bring them up to ADA standards and current plans are for the city to do the rest. At this point the city hopes to know which corners TDOT will fix.

Deteriorated sidewalks in downtown Crossville

Councilman Scot Shanks has proposed the sidewalks be repaired by bidding the project out, a scenario that is estimated to be a 9 month process versus having city employees do the work, a process that could take 3 years.

Additional items on Thursday's agenda include approving the replacement of the traffic light signal at Lantana Road and Main Street. The project will be paid for 100 percent by funds from Surface Transportation grant funds with no local match required.

And one of the air conditioning units at the Crossville airport has failed and the city is taking bids for its replacement. That action will also come before the council and budgeted funds are available.

Crossville Memorial Airport Terminal Building

Following the called meeting, the council will meet in work session to continue work on the 2017-18 budget.

Visit Park Place Motors today! 


Tuesday, August 2, 2016

City receives $500,000 grant to improve Garrison Park.

Crossville Mayor James Mayberry announced that the city has received a $500,000 grant for the re-development of the old Garrison Park of Fourth Street through the Local Parks and Recreation Fund (LPRF).

The funds have been awarded by Governor Bill Haslam and Department of Environment and Conservation commissioner Bob Martineau as part of a $16 millions in funds for use by communities for recreation improvements.

The entrance to Garrison Park and at left the old grandstands built over 50 years ago.

The grant requires a match of an additional $500,000 of local funds and will fund the first phase of a plan to provide a splash pad, playground, restrooms, renovation of the basketball court, walkways along with the removal of the existing outdated grandstand and two baseball fields.  Plans are underway to incorporate features to recognize the history of the park that was the original location of the annual county fair.

In addition, the Crossville Parks and Recreation department has been working with the ball leagues using the existing fields and they will be accommodated at Centennial Park in future years.

Phase two of the plan will include development of a multipurpose field and open plan area.  The plan for Garrison Park were part of the recreation mater plan developed by the city several years ago and the need for additional recreational facilities was mentioned in the visioning meetings held around the community.  Also, council has discussed the need for such a facility to be near the center of Crossville for easier access by low income families.

Garrison Park concept drawing from Recreation Master Plan